The design and build process

Here we explain how we work and what the implications are for you of deciding to install a pool and ancillary equipment.

Kinniburgh Pools design and build timetable

Week1

Site Survey

Design, planning and Building Warrant approval process

Weeks 2, 3

Choosing Finishes

Weeks 4, 5

Excavation

Weeks 6, 7

Pool shell

Weeks 8 - 10

Curing

Weeks 11 - 15

Pool Plant, Copings, Waterproof Render and Tiling

Week 16

Pool is Filled, Testing and Handover

Everyone asks how long does it take to build a pool? Depending upon the scale of the project, we expect a 12 to 16 week work programme, plus the time it takes to get planning and building warrant decision if these are necessary. Smaller projects of course take less time.

Site Survey - Week 1

Once you've chosen Kinniburgh Pools, we need to survey your site. If your property is on a low water table you may need to resort to extra strengthening for your pool such as piles, but we'll advise on this.

At this point we need to design then obtain planning permission and a building warrant (we prepare these for you) and we're then in the hands of your local authority who'll usually take between 6 and 16 weeks for these approvals. The planning officer might need to come out and look at your building and site, and we'll meet them with you.

Choosing Finishes - Weeks 2 and 3

We'll also use the time that your plans are with the local authority to work with you to make decisions about the pool shape, pool cover, tile finishes, surrounding tiles, stone or slates, filtration system, eco-options, landscaping and pool plant housing to create your final pool. We need to take the time on this step in the process, to get it right for you and your investment.

FoundationsExcavation - Week 4 and 5

The area that we have planning permission for will be fenced off for health and safety reasons. Digging the hole for your swimming pool takes approximately two weeks with digging equipment and removal of waste soil. Our project management skills result in an efficient excavation process and it's during this time you'll see a start to the delivery of your vision.

Pool shell - Week 6 and 7

The concrete shell for your pool is then laid down. At Kinniburgh Pools, we normally use a concrete foundation with block work walls or for intricate shapes we use a spray concrete method allowing us to create a hard, smooth shell with seamless edges.

Pool shellCuring - Week 8 - 10

Once down the concrete needs to cure for 14-30 days depending on the method in order to create a hard, solid box. We often use this time to prepare and sometimes even complete any hard landscaping work, to minimise disruption once the pool is filled and working. Bear in mind a Polypool does not need to cure thus reducing build time.

Pool Plant, Copings, Waterproof Render and Tiling - Week 11 - 15

Once the curing is complete waterproofing, rendering and tiling or lining of the whole pool can be carried out, along with the copings around the edge of the pool in order to keep the pool clean.

This is when your pool really starts to look special and you can start to feel it all coming together. Landscaping and personalising your pool are when your individuality comes in. The pool liner or tiles give the pool its character and daily, the advances make it look more like your dream.

Your pool plant equipment is installed and wired up to the pool ready for firing up once the water's in.

Pool is Filled, Testing and Handover - Week 16

During this week your pool is filled, heated, tested for security and that everything is working exactly as it should be before a full and final handover. All that remains is for you to sit back, relax and start pouring the wine, beer or soft drinks for the kids.

So that's it. Overall, your pool should take between 12-16 weeks to build and handover to you, plus the time that it takes to design then obtain planning approval and the building warrant. As with any building project, the weather and any site specific features encountered during the building process can also influence.